Vinaconex officials on trial for Da River water pipeline breaks

Share
(0 votes, average 0 out of 5)

Nine Vinaconex officials have been on a 10-day trial starting by Hanoi People's Court from March 5 following the Da River water pipeline’s 18 major water leaks caused by low-quality construction.

Vinaconex officials on trial for Da River water pipeline breaks, social news, vietnamnet bridge, english news, Vietnam news, news Vietnam, vietnamnet news, Vietnam net news, Vietnam latest news, vn news, Vietnam breaking news

Da River pipeline broke for 18 times

 

They were all charged with breaching construction regulations causing serious consequences.

The Da River Water Pipeline Project is a build-own-operate project invested by Vinaconex and was built from 2004 to 2009. 

However, from 2012 to 2016, the pipeline broke for 18 times. 

Repair work cost more than VND16.6bn (USD731,000). About 177,000 households, many hospitals and other public services in Hanoi were affected by water shortages for 386 hours.

The inspection results in 2015 showed that various violations had been committed in the pipeline manufacturing, construction management and supervision. 

The pipes were low quality in some sections, and the management board failed to test the pipeline quality before installation, noticing the violations during the construction or the repair work after breakdowns.

  Vinaconex officials on trial for Da River water pipeline breaks, social news, vietnamnet bridge, english news, Vietnam news, news Vietnam, vietnamnet news, Vietnam net news, Vietnam latest news, vn news, Vietnam breaking news

Defendants in court on March 5

 

The Supreme People's Procuratorate said former director of the management board of the Da River water supply construction and investment project Hoang The Trung, former deputy director Nguyen Van Khai, former supply division head Truong Tran Hien along with Tran Cao Bang, former director of the Vinaconex Glass Fibre Reinforced Polyester Pipe Company, and deputy director Vu Thanh Hai had signed 73 minutes of acceptance and gave approval to over 5,000 pipe sections for the project.

Do Dinh Tri, former head of the consultant and monitoring team of the Vietnam Water, Sanitation and Environment Company, was responsible for monitoring the construction and gave approval to the quality of the pipes as well as the work as in accordance with the original plan.

Nguyen Bien Hung, Hoang Quoc Thong and Bui Minh Quan, former employees at Vietnam Water, Sanitation and Environment Company were also on the trial.

 

 

Source: Dtinews 

Maybe You Also Interesting :

» SCIC may continue divestment in Vinaconex in 2018

State-owned investment fund State Capital Investment Corporation (SCIC) may offload its stakes in Việt Nam Construction and Import-Export Joint Stock...

» SCIC sells 5.6 per cent stake at Vinaconex

The State Capital Investment Corporation (SCIC) collected VNĐ137 billion (US$6 million) after auctioning 5.35 million shares of Việt Nam Construction and...